Beads Integration Action Summary

Date: January 2, 2026
Status: Ready to Execute
Document: See docs/design/GIL_RELEASE_HYBRID_IMPLEMENTATION_PLAN_WITH_BEADS_MAPPING.md for full details


Critical Issues Found

1. Phase C Epic: Lacks Subtasks (Critical)

  • Current State: mrrc-ppp epic exists but has NO subtasks
  • Plan Requirement: 6 subtasks (C.0 through C.Gate) with dependency chain
  • Impact: Cannot track progress; no clear definition of work

2. Duplicate Phase C Epic (Cleanup)

  • Current State: Both mrrc-ppp and mrrc-d0m (identical title)
  • Action: Close mrrc-d0m with reason "Duplicate of mrrc-ppp"

3. Phase H Epic: Does Not Exist (Critical)

  • Current State: No Phase H epic or subtasks in beads
  • Plan Requirement: 1 epic + 10 subtasks with full dependency chain
  • Impact: Phase H work cannot be tracked or prioritized

4. Diagnostic Infrastructure: Missing (High)

  • Current State: No tasks for test suite setup or memory safety CI
  • Plan Requirement: Explicit infrastructure tasks for C.0 and C.Gate gates
  • Tasks Needed:
  • Infrastructure: Diagnostic Test Suite (tests/concurrent_gil_tests.rs, scripts/benchmark_batch_sizes.py, etc.)
  • Infrastructure: Memory Safety - ASAN/Valgrind CI Integration

5. Phase G Dependency: Incorrect (Medium)

  • Current State: Phase G only depends on Phase F
  • Plan Requirement: Phase G must also depend on Phase H.Gate
  • Action: Update mrrc-9wi.6 description to reference Phase H.Gate blocker

6. Batch Size Gate Criterion: Inconsistent (Medium)

  • Current State: Phase F (mrrc-pfw) references ≥2.0x speedup for Phase C decision
  • Plan Requirement: Phase C.Gate uses ≥1.8x speedup as target
  • Action: Clarify that Phase F is pre-C; Phase C.Gate is post-C with 1.8x target

Required Beads Operations

Immediate (Today)

1. Create Phase C Subtasks under mrrc-ppp

# C.0: Foundation (1 day)
bd create "C.0: Data Structure, State Machine & GIL Verification Test" \
  --parent mrrc-ppp -t task -p 1 --deps discovered-from:mrrc-18s

# C.1: read_batch (1-2 days) - depends on C.0
bd create "C.1: Implement read_batch() Method with Single GIL Cycle" \
  --parent mrrc-ppp -t task -p 1

# C.2: Queue FSM (1 day) - depends on C.1
bd create "C.2: Update __next__() to Use Queue & EOF State Machine" \
  --parent mrrc-ppp -t task -p 1

# C.3: Idempotence (1 day) - depends on C.2
bd create "C.3: Iterator Semantics & Idempotence Verification" \
  --parent mrrc-ppp -t task -p 1

# C.4: Memory Profiling (1 day) - parallel with C.2-C.3
bd create "C.4: Memory Profiling & Bounds Validation" \
  --parent mrrc-ppp -t task -p 2

# C.Gate: Benchmarking (1 day) - depends on C.3, C.4
bd create "C.Gate: Benchmark Batch Sizes (10-500 sweep) - ≥1.8x Speedup Gate" \
  --parent mrrc-ppp -t task -p 1

2. Create Phase H Epic + All Subtasks

# Phase H Epic (depends on C.Gate)
H_EPIC=$(bd create "Phase H: Pure Rust I/O & Rayon Parallelism" \
  -t epic -p 1 --deps discovered-from:mrrc-ppp.Gate --json | jq -r '.id')

# H.0: Rayon PoC (1 day) - can start immediately, independent
bd create "H.0: Rayon PoC - Thread Pool & Channel Pipeline Validation" \
  --parent $H_EPIC -t task -p 1

# H.1: Type Detection (1 day) - depends on H.0
bd create "H.1: ReaderBackend Enum & Type Detection Algorithm" \
  --parent $H_EPIC -t task -p 1

# H.2: RustFile Backend (1-2 days) - depends on H.1
bd create "H.2: RustFile Backend Implementation - Sequential Read" \
  --parent $H_EPIC -t task -p 1

# H.2b: CursorBackend (1 day) - depends on H.1
bd create "H.2b: CursorBackend Implementation - Memory-Mapped & Bytes" \
  --parent $H_EPIC -t task -p 1

# H.3: Sequential Baseline (1 day) - depends on C.Gate, H.2, H.2b
bd create "H.3: Sequential Baseline & Parity Tests (RustFile + CursorBackend)" \
  --parent $H_EPIC -t task -p 1

# H.4a: Boundary Scanner (1 day)
bd create "H.4a: Record Boundary Scanner (0x1E delimiter + multi-threaded)" \
  --parent $H_EPIC -t task -p 1

# H.4b: Rayon Parser Pool (1 day) - depends on H.4a
bd create "H.4b: Rayon Parser Pool - Parallel Batch Processing" \
  --parent $H_EPIC -t task -p 1

# H.4c: Producer-Consumer Pipeline (1-2 days) - depends on H.4b
bd create "H.4c: Producer-Consumer Pipeline - Backpressure & Channels" \
  --parent $H_EPIC -t task -p 1

# H.5: Integration Tests (1 day) - depends on H.4c
bd create "H.5: Integration Tests & Error Propagation Validation" \
  --parent $H_EPIC -t task -p 1

# H.Gate: Parallel Benchmarking (1 day) - depends on H.5
bd create "H.Gate: Parallel Benchmarking - ≥2.5x Speedup (4-thread) Gate" \
  --parent $H_EPIC -t task -p 1

3. Create Infrastructure Tasks

# Diagnostic Test Suite (prerequisite to C.0)
bd create "Infrastructure: Diagnostic Test Suite (GIL verification, benchmarking utilities)" \
  -t task -p 1

# Memory Safety CI (prerequisite to C.4)
bd create "Infrastructure: Memory Safety - ASAN/Valgrind CI Integration" \
  -t task -p 2

Soon (Within 2 hours)

4. Update Phase G Description

Edit mrrc-9wi.6 to add: - Blocker: Phase H.Gate must complete - Doc sections: Add Phase H threading model, RAYON_NUM_THREADS tuning, backpressure explanation

5. Update Phase F Description (Optional)

Add note: "Phase C decision gate uses ≥1.8x speedup criterion (after Phase C implementation). This Phase F benchmark informs whether Phase C is needed at all."


Dependency Summary

Current Phase Chain:
A (Buffer) → B (GIL Release) → D (Writer) → E (Validation) → F (Benchmarks) → G (Docs)

Revised Chain with Phase C & H:
A → B → D → E → F → [Decision: Phase C needed?]
            Phase C → H.0 PoC
                ↓        ↓
            C.Gate    H.1-H.2b (parallel)
                ↓        ↓
            H.3 ← ─ ─ ─┘
            H.4a-c
            H.Gate
                G (Docs)

Critical Blockers: - C.Gate blocks H.3 (sequential baseline needs C complete) - H.Gate blocks Phase G release (docs must cover Phase H threading model)


Metrics & Gates

Gate When Target Blocker
C.Gate End of Phase C ≥1.8x speedup (2-thread) Blocks H.3 start
H.Gate End of Phase H ≥2.5x speedup (4-thread) Blocks Phase G release

Estimated Timeline

Phase Duration Status Blocker
Phase C (full) 5 days Ready to start None (can start Day 1)
Phase H.0 PoC 1 day Can start immediately None
Phase H.1-H.2b 3 days Can start Day 1 None (H.0 completion advised)
Phase H.3 1 day Can start Day 6 Waits for C.Gate pass
Phase H.4a-c 3 days Can start Day 7 H.3 completion
Phase H.Gate 1 day Day 10 H.5 completion
Total (serial) 14 days - -
Total (optimized) 8-9 days - C.Gate + 1 day for H.3 delay

Document References

Full details in: docs/design/GIL_RELEASE_HYBRID_IMPLEMENTATION_PLAN_WITH_BEADS_MAPPING.md

Sections: - §1: Detailed beads mapping (what exists, what's missing) - §2: Beads operations (deletions, creations, updates) - §3: Task breakdown with plan references (§3.1-3.4 for C, §4 for H) - §4: Existing phase updates (E, F, G) - §5: Sequencing recommendations (critical path, parallel opportunities) - §6: Metrics & gates - §7: Next steps (immediate actions)


Before You Start

  1. Review GIL_RELEASE_HYBRID_IMPLEMENTATION_PLAN_REVISIONS.md (original detailed plan)
  2. Review this summary + full mapping document
  3. Run beads commands above in order
  4. Verify dependency chain: bd dep show mrrc-ppp && bd dep show $H_EPIC
  5. Start with Phase C (Day 1) or Phase H.0 PoC (Day 1) in parallel

Ready to Execute: Yes
Confidence Level: High (all gaps identified, all tasks specified, all dependencies documented)
Questions: Refer to detailed mapping document; all §/line references verified against original plan